Suffolk Highways’ time frame for A1088 Bridge Farm Bridge, at Stowlangtoft, near Bury St Edmunds, restoration provisionally extended for two months
The time frame for works to restore a bridge on a key road have been provisionally extended by two months.
Suffolk Highways announced today it was updating its construction programme for the project at the A1088 Bridge Farm Bridge, in Stowlangtoft, and as such had provisionally extended its road space booking until February 28, 2025.
The works were originally forecast to finish by December this year.
A definite revised completed date has not yet been finalised.
Explaining the update and provisional extension, Highways said: “We are hopeful that this will allow sufficient time for us to rectify the issues identified with the concrete and complete construction of the new bridge, however this date may be subject to change if there are prolonged periods of cold and wet weather during the winter.”
“We apologise for any ongoing inconvenience caused by this unforeseen delay and would also like to thank the local community for their continued patience in the interim.”
Businesses in Norton and Stowlangtoft have deplored the delays the the project.
Works on the bridge restarted this week after they delayed when defects were found with concrete piles used in the construction.
Highways said seven new piles have now been installed to support the northern side of the structure, which will enable works to construct the new bridge abutments and deck to progress.